Environmental Protection
43 initiatives across 4 years
Underway this year
7
1 with disruption at end of March 2026
Delivery record
10 of 29
past initiatives completed · 11 on track, not yet complete
2026–27not started yet
2025–264 initiatives
2024–2513 initiatives · 4 finished on time
1.1.2 Management of bio basins · ended the year with minor disruption
Delivery of the maintenance schedule was delayed in Q3 due to adverse weather, and the programme was unable to recover these delays in Q4.
1.2.3 Biosecurity · ended the year with minor disruption
A draft is currently being reviewed; however, staff resources have been limited due to balancing competing operational demands. Completion anticipated in Q1/2 FY25/26.
1.3.3 High-risk erosion areas · ended the year with minor disruption
Progress through the High-Risk Erosion Prone Area Working Group has stalled due to staff vacancy and changes. A Noosa Eastern Beaches Creek Erosion Risk study has been delivered by consultants, covering geotechnical, hydrological & vegetation assessments at the nine creeks along the Eastern Beaches. Assessments were used to identify slope stability risks as well as urgent, short, medium and long term actions to reduce these risks. Actions vary from urgent remediation works through to longer term revegetation and weed control.
1.6.1 Noosa River Catchment Action Plan · ended the year with major disruption
Delayed to FY2025/26. This initiative will now be advanced as part of the SEQ Resilient Rivers Program for preparing a Catchment Action Plan. Council is being supported with funding via Resilient Rivers and resourcing to assist in preparing the Noosa River Catchment Management Plan. Community engagement on a Draft plan will occur in 2026.
1.7.1 Threatened Fauna Roadmap · ended the year with minor disruption
Action Plans for Koala Conservation and Sea Turtle are nearing completion (95%).
1.7.2 Koala Conservation Plan · ended the year with minor disruption
The final draft has been completed and is undergoing internal review in Q1 FY25/26.
2023–2412 initiatives · 5 finished on time
1.3.5 Encroachments Policy · ended the year with minor disruption
Program mostly set up with minor delay due to staff turnover. Note-relisted in the new 24/25 Operational Plan
2026–27not started yet
2025–261 initiative
2024–251 initiative · 1 finished on time
2026–27not started yet
2025–262 initiatives
2024–251 initiative · 0 finished on time
2023–242 initiatives · 0 finished on time
4.2.1 Destination Management Plan · ended the year with minor disruption
Deep Dive Analysis completed. Community Engagement Phase 2 scheduled for August/September 2024. Note-relisted in the new 24/25 Operational Plan