Burgess Creek
Partner with Unitywater to develop an Integrated Water Catchment Management Plan for Burgess Creek that will provide a strategic framework for hydrological, environmental and recreational improvement for the catchment area.
Quarterly updates
Q3 · On Track
Stakeholder and community engagement plan completed, and consultants for its delivery have been engaged. Technical report in final draft and distributed to stakeholders. Three community and stakeholder engagement sessions held in March and Action Plan currently in drafting stage to be taken to Council in May, prior to wider community consultation via 'Your Say' in June. On track for completion and final endorsement by end of the calendar year.
Q2 · On Track
This project is funded by the State Government. The stakeholder and community engagement plan has been finalised, and consultants have been engaged to deliver the program.
Q1 · On Track
Funding contract and project inception meeting completed with DETSI. Project Control Group will begin meeting from October 2025.
Q4 is not due yet.
Where this sits
Initiative 1.1.1 is from the 2025–26 operational plan and works towards Environment Objective 1.1: Water quality.
Latest status: January to March 2026 · On Track