Operational Plan
2024-25
›
Initiative 1.3.4: Implement the Encroachments Policy and Operational procedure, including the development of a community education and awareness campaign to guide community use and management of council managed land.
Q1:Minor Disruption
recruitment of Natural Areas Recovery Officer was delayed (interviewing mid-Oct). Education material has been developed.
Q2:On Track
Recruitment finalised, education material finalised, recovery project underway.
Q3:On Track
Recovery projects undertaken at Lorikeet Drive and Mulloway St., Teewah. Communication material finalised and distribution has been focused on high value areas. Implementation initiatives occurring within allocated budget and resourcing.
Q4:On Track
Ongoing implementation program underway. Recovery plans have been developed for the esplanade south of the ferry – associated works to be undertaken in FY25/26. Works at Lorikeet Dr, Peregian Beach, have been completed.
Noosa Shire Council
Operational Plan
2024-25Initiative 1.3.4: Implement the Encroachments Policy and Operational procedure, including the development of a community education and awareness campaign to guide community use and management of council managed land.
Q1: Minor Disruption
Q2: On Track
Q3: On Track
Q4: On Track
recruitment of Natural Areas Recovery Officer was delayed (interviewing mid-Oct). Education material has been developed.
Recruitment finalised, education material finalised, recovery project underway.
Recovery projects undertaken at Lorikeet Drive and Mulloway St., Teewah. Communication material finalised and distribution has been focused on high value areas. Implementation initiatives occurring within allocated budget and resourcing.
Ongoing implementation program underway. Recovery plans have been developed for the esplanade south of the ferry – associated works to be undertaken in FY25/26. Works at Lorikeet Dr, Peregian Beach, have been completed.