Underway this year

4

1 with disruption at end of March 2026

Completed this year

2

Delivery record

3 of 7

past initiatives completed · 2 on track, not yet complete

2026–27not started yet
2025–264 initiatives
5.3.2 Streamlined development assessmentQ3 · Minor Disruption · Initial scoping of potential processes is currently underway. Project workshop was scheduled for the end of Q3, however was not able to proceed due to staff vacancies (recruitment currently underway).
5.3.3 Council operations improvementQ3 · On Track · Key departments have engaged Business Improvement Officers to work with the ICT counterparts in identifying efficiencies, potential system upgrades, and new system requirements. The rollout of system enhancements across the organisation is progressing well, with ongoing improvements being implemented across departments. Implementation of EftSure as a fraud reduction measure has been initiated during the reporting period. Negotiations with Council's main technology provider continue to ensure that services meet Council demands.
5.3.4 Council systemsQ3 · Completed

Initiatives from previous years

These initiatives have been archived — they are no longer being updated.

2024–254 initiatives · 1 finished on time

5.3.2 Local Laws review · ended the year with major disruption

Councillor Workshop held 1 May 2025 which discussed various review options.

5.3.1 Council ICT and Digital StrategyQ4 · On Track · Resourcing constraints and competing priorities have limited progress but the initiative has regained traction in this quarter.
5.3.4 Council operations improvementQ4 · On Track · Key departments have engaged business improvement officers to link in with ICT Business Improvement Officer to identify efficiencies and possible system upgrades or new systems requirements. The rollout of the system improvements is progressing well, and implementation is expected as programmed.
2023–243 initiatives · 2 finished on time

5.3.1 Council ICT and Digital Strategy · ended the year with minor disruption

New ICT Management leading development of new ICT and Digital Strategy. Baseline assessment complete. Note-relisted in the new 24/25 Operational Plan

5.3.2 Licence plate recognitionQ4 · Completed · Procurement of the vehicle, LPR technology, systems and communications plan complete. LPR systems implemented 20 April 2024. Final in configuration being completed. Project has been subject to slight delays due to ICT integration and PR challenges. Scheduled to 'Go Live" on 22 July 2024.
5.3.3 Noosa Libraries appQ4 · Completed · Over 1000 registered users and over 100,000 app interactions since launching the app in November 2023.

Council meetings that mention this

Found by matching meeting agendas — worth checking, not guaranteed.

11/12/25

Special Meeting 11 December 2025

Transcript: Noosa Watch | Files: Noosa Council

In the files, see: Report.pdf (around page 5)
13/5/24

General Committee Meeting 13 May 2024

Transcript: Noosa Watch | Files: Noosa Council

In the files, see: Report.pdf (around page 3)
16/11/23

Ordinary Meeting 16 November 2023

Transcript: Noosa Watch | Files: Noosa Council

In the files, see: Report.pdf (around page 3)

Explore by topic

Where this sits

This objective is part of Theme 5: Excellence, in the 2023-28.