Q1:On Track
Connection agreement and contract with energy supplier signed in October 2025. Installation proposed December 2025.
Q2:On Track
Connection agreement and contract with energy supplier signed in October 2025. Installation anticipated February 2026.
Q3:Unknown
Q4:Unknown
Q1: On Track
Q2: On Track
Connection agreement and contract with energy supplier signed in October 2025. Installation proposed December 2025.
Connection agreement and contract with energy supplier signed in October 2025. Installation anticipated February 2026.