Community Battery
FY 2022–23
Q1
Q2
Q3
Q4
4.7.3 Deliver the community battery for Noosaville and identify further strategic locations across Noosa LGA for Community Batteries, microgrid opportunities, EV charging in readiness for future grant funding.
Q1
Q2
Site investiagtions for appropriate and feasible location still occuring.
Q3
Q4
A minor disruption to the community battery progress, awaiting outcomes of advocacy around Energex tariff structure to ensure the viability of the project. Note-Ongoing and part of BAU
FY 2024–25
Q1
Q2
Q3
Q4
5.2.3 Deliver the Community Battery project
Q1
Connection agreement and contract with energy supplier signed in October 2025. Installation proposed December 2025.
Q2
Connection agreement and contract with energy supplier signed in October 2025. Installation anticipated February 2026.