High-risk erosion areas
Prepare an ongoing management program for high-risk erosion prone areas of the Climate Change Adaption Plan (CHAP).
Quarterly updates
Q3 · Minor Disruption
Contract awarded and construction commenced for Sunshine Creek. Ground conditions require a design revision and revised construction methodology. Continued risk to timing being managed. Other coastal erosion mitigation works are dependent on funding for revegetation works to Council's Strategy and Environment team.
Q2 · On Track
Tender to select slope stability contractors for Sunshine Creek bank stabilisation design is in progress. Continued risk to timing being managed via actions such as proposed Councillor Special Meeting for Contract approval. Other coastal erosion mitigation works are dependent on funding for revegetation works to Council's Strategy and Environment team.
Q1 · Minor Disruption
Sunshine Creek bank stabilisation design is near finalisation following further design review and will be going to tender in near future. Other coastal erosion mitigation works are dependant on funding for revegetation works to Council's Environment team.
Q4 is not due yet.
Where this sits
Initiative 4.8.4 is from the 2025–26 operational plan and works towards Future Objective 4.8: Disaster Management.
Latest status: January to March 2026 · Minor Disruption