Climate Change Adaptation Plan
1 initiative across 1 year
Underway this year
1
1 with disruption at end of March 2026
2025–261 initiative
4.8.4 High-risk erosion areasQ3 · Minor Disruption · Contract awarded and construction commenced for Sunshine Creek. Ground conditions require a design revision and revised construction methodology. Continued risk to timing being managed. Other coastal erosion mitigation works are dependent on funding for revegetation works to Council's Strategy and Environment team.