erosion
3 initiatives across 3 years
Underway this year
1
1 with disruption at end of March 2026
Delivery record
0 of 2
past initiatives completed · 1 on track, not yet complete
2024–251 initiative · 0 finished on time
1.3.3 High-risk erosion areas · ended the year with minor disruption
Progress through the High-Risk Erosion Prone Area Working Group has stalled due to staff vacancy and changes. A Noosa Eastern Beaches Creek Erosion Risk study has been delivered by consultants, covering geotechnical, hydrological & vegetation assessments at the nine creeks along the Eastern Beaches. Assessments were used to identify slope stability risks as well as urgent, short, medium and long term actions to reduce these risks. Actions vary from urgent remediation works through to longer term revegetation and weed control.