Beckmans Road
Progress design development of the Beckmans Road duplication in collaboration with the Department of Transport and Main Roads (DTMR).
Quarterly updates
Q3 · On Track
The preferred corridor option has been identified with staging and intersection options review underway in collaboration with DTMR. Federal environmental approval submission and community engagement program is currently being prepared.
Q2 · On Track
The review of design options is well advanced, with recent internal staff and Councillor workshops to inform evaluation. Additional dedicated resources have been appointed to lead the design review process to meet DTMR timelines for the design program.
Q1 · On Track
The review of design options is well advanced, with recent internal staff and Councillor workshops to inform evaluation. Additional dedicated resources have been appointed to lead the design review process to meet DTMR timelines for the design program.
Q4 is not due yet.
Where this sits
Initiative 2.4.1 is from the 2025–26 operational plan and works towards Liveability Objective 2.4: Transport improvement.
Latest status: January to March 2026 · On Track