Noosa Trails
Continue to support the planning and delivery of the maintenance programs for the Noosa Trails network (also relates to 2.2.2)
Quarterly updates
Q4 · Completed
Maintenance program successfully completed. Planning support delivered for significant trail 5 upgrade and ongoing planning for trail extension to Boreen Point.
Q3 · On Track
Q2 · On Track
Operational Maintenance Plan (Asset Management Plan) is underway. Tender documentation has been issued for upgrades to Trail 7 and signage upgrades on Trail 7 are also being developed.
Q1 · On Track
Where this sits
Initiative 2.4.6 is from the 2023–24 operational plan and works towards Liveability Objective 2.4: Transport improvement.
This initiative is from a past year and is no longer being updated.