Flood resilience

Advance flood resilience projects including updating the Noosa River Flood Study, Six Mile Creek Flood Study and Noosa Flood Management Operational Plan.

Quarterly updates

Q4 · Minor Disruption · April to June 2024 · latest

Flood Management Operational Plan in final draft. Noosa River Flood Study and Six Mile Creek Flood Study updates are on track with ITQ now closed and tender evaluation and award to be completed within Q1. Estimated completion June 2025. Note-relisted in the new 24/25 Operational Plan

Q3 · On Track · January to March 2024

Q2 · On Track · October to December 2023

First draft Flood Management Plan complete, Pomona Flood risk mitigation plan udnerway. Scoping study for flood study updates complete. ITQ for two flood studies being prepared, ANU nature based solutions project on track.

Q1 · On Track · July to September 2023

Where this sits

Initiative 4.8.5 is from the 2023–24 operational plan and works towards Future Objective 4.8: Disaster Management.

This initiative is from a past year and is no longer being updated.