Flood resilience

Advance flood resilience projects including updating the Noosa River Flood Study, Six Mile Creek Flood Study and Noosa Flood Management Plan.

Quarterly updates

Q3 · On Track · January to March 2026 · latest

Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 outcomes due by June 2026. Resident consultation undertaken 24 March 2026. Implementation of the Noosa Flood Management Operational Plan continues with internal working group.

Q2 · On Track · October to December 2025

Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 commenced November 2025 and due by June 2026. Implementation of the Noosa Flood Management Operational Plan commenced with internal working group.

Q1 · Minor Disruption · July to September 2025

Minor disruptions due to staff resourcing and capacity. Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 commencing November 2025. Noosa Flood Management Operational Plan prepared for implementation with internal working group.

Q4 is not due yet.

Where this sits

Initiative 4.8.8 is from the 2025–26 operational plan and works towards Future Objective 4.8: Disaster Management.

Latest status: January to March 2026 · On Track