Operational Plan
2024-25
›
Initiative 4.8.3: Complete the implementation of the Disaster Recovery Plan for the 2022 Floods & Rain Event.
Q1:On Track
All landslide reconstruction completed except for Black Mountain Rd, Black Pinch Rd and Upper Pinbarren Creek Rd. Those projects are on track. All waterway crossing reconstruction completed except for Schreibers Rd Bridge Betterment project. This project has recently commenced constructon with possession of site.
Q2:On Track
Remaining reconstruction projects underway. Human social Recovery Plan completed.
Q3:On Track
Final reconstruction projects near completion. Human social Recovery Plan completed.
Q4:On Track
Majority of reconstruction projects complete including major Black Mountain landslip. Final reconstruction project near completion. Human social Recovery Plan completed.
Noosa Shire Council
Operational Plan
2024-25Initiative 4.8.3: Complete the implementation of the Disaster Recovery Plan for the 2022 Floods & Rain Event.
Q1: On Track
Q2: On Track
Q3: On Track
Q4: On Track
All landslide reconstruction completed except for Black Mountain Rd, Black Pinch Rd and Upper Pinbarren Creek Rd. Those projects are on track. All waterway crossing reconstruction completed except for Schreibers Rd Bridge Betterment project. This project has recently commenced constructon with possession of site.
Remaining reconstruction projects underway. Human social Recovery Plan completed.
Final reconstruction projects near completion. Human social Recovery Plan completed.
Majority of reconstruction projects complete including major Black Mountain landslip. Final reconstruction project near completion. Human social Recovery Plan completed.