THEME 2: Liveability
Objective 2.4: Advocate and partner with all levels of government for increased funding for connected transport nodes, transit hubs, including walking, cycling and public transport and explore opportunities through smart city, smart biosphere and innovation to transform the way we move around and engage in our community.
Operational Plan
2023-24
›
Initiative 2.4.5: Accelerate delivery of the Cycling and Walking Implementation Plan.
Q1:Minor Disruption
Noosa Woods pathway (including connection to Sofitel boardwalk) & Path widening at Memorial Park, Tewantin are scheduled for delivery in November & February respectively; Design finalisation of missing links (Boreen Point, Factory St, Kauri St, Grifith Ave) to be fast tracked for delivery in Q4 of 23/24 FY; approx. $1million allocated to pathway asset renewals this FY - this is being aligned with Walking & Cycling Strategy to deliver increased level of service (widening) where appropriate; Walking Network Plans for Cooroy Train Station & Good Shepherd School Noosaville are under development & are to be finalised in Q2 following incorporation of feedback from TMR & Internal stakeholders.
Q2:Minor Disruption
Construction of Noosa Woods pathway (including connection to Sofitel boardwalk) is nearing completion. Path widening at Memorial park Tewantin is currently scheduled for delivery in February; Design finalisation of missing links (Boreen point, kauri St, Grifith Ave) being fast tracked and still currently scheduled for delivery in Q4 of 23/24 FY. Factory Street missing link has been delayed to allow further investigation & community consultation; approx. $1million of pathway asset renewals currently underway this FY - Delivery is being aligned with Walking & Cycling Strategy to deliver increased level of service (widening) where appropriate. Council has also sought funding for coastal pathway funding under the SEQ Liveability Fund and optimistic of outcomes Walking Network Plans for Cooroy Train Station & Good Shepherd School Noosaville have been finalised and will be submitted to Council for endorsement in Q3. Priority works Schedule recommendations are being finalised following incorporation of feedback from TMR & Internal stakeholders.
Q3:Minor Disruption
A detailed application to the SEQ Livability Fund as been submitted for the Peregian Beach Coastal Cycle Street & Pathway Stage 1 and Wayfinding Signage and Minor Pathways. Note-as previously reported
Q4:Minor Disruption
A detailed application to the SEQ Liveability Fund as been submitted for the Peregian Beach Coastal Cycle Street & Pathway Stage 1 and Wayfinding Signage and Minor Pathways with announcement of outcomes expected in the new financial year. Delivery of pathways within the C&W Program continue to be scheduled in the 10-year capital works program according to priority and available funding. Note-relisted in the new 24/25 Operational Plan
Noosa Shire Council
Operational Plan
2023-24Initiative 2.4.5: Accelerate delivery of the Cycling and Walking Implementation Plan.
Q1: Minor Disruption
Q2: Minor Disruption
Q3: Minor Disruption
Q4: Minor Disruption
Noosa Woods pathway (including connection to Sofitel boardwalk) & Path widening at Memorial Park, Tewantin are scheduled for delivery in November & February respectively; Design finalisation of missing links (Boreen Point, Factory St, Kauri St, Grifith Ave) to be fast tracked for delivery in Q4 of 23/24 FY; approx. $1million allocated to pathway asset renewals this FY - this is being aligned with Walking & Cycling Strategy to deliver increased level of service (widening) where appropriate; Walking Network Plans for Cooroy Train Station & Good Shepherd School Noosaville are under development & are to be finalised in Q2 following incorporation of feedback from TMR & Internal stakeholders.
Construction of Noosa Woods pathway (including connection to Sofitel boardwalk) is nearing completion. Path widening at Memorial park Tewantin is currently scheduled for delivery in February; Design finalisation of missing links (Boreen point, kauri St, Grifith Ave) being fast tracked and still currently scheduled for delivery in Q4 of 23/24 FY. Factory Street missing link has been delayed to allow further investigation & community consultation; approx. $1million of pathway asset renewals currently underway this FY - Delivery is being aligned with Walking & Cycling Strategy to deliver increased level of service (widening) where appropriate. Council has also sought funding for coastal pathway funding under the SEQ Liveability Fund and optimistic of outcomes Walking Network Plans for Cooroy Train Station & Good Shepherd School Noosaville have been finalised and will be submitted to Council for endorsement in Q3. Priority works Schedule recommendations are being finalised following incorporation of feedback from TMR & Internal stakeholders.
A detailed application to the SEQ Livability Fund as been submitted for the Peregian Beach Coastal Cycle Street & Pathway Stage 1 and Wayfinding Signage and Minor Pathways. Note-as previously reported
A detailed application to the SEQ Liveability Fund as been submitted for the Peregian Beach Coastal Cycle Street & Pathway Stage 1 and Wayfinding Signage and Minor Pathways with announcement of outcomes expected in the new financial year. Delivery of pathways within the C&W Program continue to be scheduled in the 10-year capital works program according to priority and available funding. Note-relisted in the new 24/25 Operational Plan