Community buildings and infrastructure

Continue to progress asset management planning for Council's community services buildings and community infrastructure to ensure their ongoing suitability to meet the functional needs of current and future users.

Quarterly updates

Q3 · Minor Disruption · January to March 2026 · latest

Building Condition Assessment Reports (BCARs): 71% completed. With the inclusion of a new facility in scope, completion adjusts to 62.5%. Comprehensive Asset Management Plans (AMPs): 28% nearing completion, with progress currently constrained by available resourcing. Progress has been impacted by competing priorities from internal stakeholders across work programs.

Q2 · Minor Disruption · October to December 2025

Building condition assessment reports (BCARs) 57% completed with further BCARs delayed due to limited resourcing. Additional BCAR completed December 2025. 28% of comprehensive Asset Management Plans (AMPs) near completion. Progress constrained by available resourcing.

Q1 · Minor Disruption · July to September 2025

Building condition assessment reports (BCARs) 40% completed with further BCARs delayed due to limited resourcing. Additional BCARs to be undertaken from October 2025 with one due for completion by December 2025. 28% of comprehensive Asset Management Plans (AMPs) near completion. Progress constrained by available resourcing.

Q4 is not due yet.

Where this sits

Initiative 2.7.5 is from the 2025–26 operational plan and works towards Liveability Objective 2.7: Sustainable facilities.

Latest status: January to March 2026 · Minor Disruption