Operational Plan 2024-25
Initiative 2.7.4: Continue to progress asset management planning for council's community services buildings and community infrastructure to ensure their ongoing suitability to meet the functional needs of current and future users.
Q1:Minor Disruption
Audit of existing facilities asset management documentation complete. Detailed condition assessments commenced. Remaining condition assessments require additional resourcing.
Q2:Minor Disruption
Comprehensive building condition assessments underway however constrained by available resourcing.
Q3:Minor Disruption
Building condition assessment reports (BCARs) 40% completed with further BCARs underway. 28% of comprehensive Asset Management Plans (AMPs) near completion. Progress constrained by available resourcing. Budget request submitted.
Q4:Minor Disruption
Building condition assessment reports (BCARs) 40% completed with further BCARs delayed due to limited resourcing. Additional BCARs expected to recommence by the end of August 2025 with one due for completion by December 2025. 28% of comprehensive Asset Management Plans (AMPs) near completion. Progress constrained by available resourcing.
Noosa Shire Council
Operational Plan
2024-25
Initiative 2.7.4: Continue to progress asset management planning for council's community services buildings and community infrastructure to ensure their ongoing suitability to meet the functional needs of current and future users.
Q1: Minor Disruption
Q2: Minor Disruption
Q3: Minor Disruption
Q4: Minor Disruption
Audit of existing facilities asset management documentation complete. Detailed condition assessments commenced. Remaining condition assessments require additional resourcing.
Comprehensive building condition assessments underway however constrained by available resourcing.
Building condition assessment reports (BCARs) 40% completed with further BCARs underway. 28% of comprehensive Asset Management Plans (AMPs) near completion. Progress constrained by available resourcing. Budget request submitted.
Building condition assessment reports (BCARs) 40% completed with further BCARs delayed due to limited resourcing. Additional BCARs expected to recommence by the end of August 2025 with one due for completion by December 2025. 28% of comprehensive Asset Management Plans (AMPs) near completion. Progress constrained by available resourcing.