Q1:On Track
Q2:On Track
Part-time Project Officer appointed to support Asset Management Planning for Community Services. Collation of available AM data and documents underway.
Q3:On Track
Q4:Minor Disruption
Audit of existing community services asset management components complete. Identified need for better quality, relevant condition assessments which can reliably inform asset management for individual facilities. The condition assessments are underway. Note-relisted in the new 24/25 Operational Plan
Noosa Shire Council
Operational Plan
2023-24
Initiative 2.7.1: Progress Asset Management Planning for Council's community services buildings and community infrastructure.
Q1: On Track
Q2: On Track
Q3: On Track
Q4: Minor Disruption
Part-time Project Officer appointed to support Asset Management Planning for Community Services. Collation of available AM data and documents underway.
Audit of existing community services asset management components complete. Identified need for better quality, relevant condition assessments which can reliably inform asset management for individual facilities. The condition assessments are underway. Note-relisted in the new 24/25 Operational Plan