Operational Plan
2025-26
›
Initiative 1.3.3: Implement the Encroachment Policy and restoration program
Q1:On Track
Programme continuing within resource allocation in close liaison with Local Laws team to manage encroachments. Medium scale reclamation and rehabilitation currently underway on Noosa River Esplanade in Tewantin.
Q2:On Track
Annual implementation program. This initiative is on track including the delivery of community education and remedial works to the Noosa River Esplanade and other emerging localities.
Q3:Unknown
Q4:Unknown
Noosa Shire Council
Operational Plan
2025-26Initiative 1.3.3: Implement the Encroachment Policy and restoration program
Q1: On Track
Q2: Major Disruption
Programme continuing within resource allocation in close liaison with Local Laws team to manage encroachments. Medium scale reclamation and rehabilitation currently underway on Noosa River Esplanade in Tewantin.
Consultant engagement and design work for Boreen Point Campground master planning completed. Project scope is currently on hold due to identified challenges in obtaining development approval under the current scope and scale. Further progression paused pending resolution of planning constraints and review of alternative options in 25/26.