emissions reduction
7 initiatives across 3 years
Underway this year
2
1 with disruption after Q3
Delivery record
0 of 5
past initiatives completed
4.7.1
Q3 · Minor Disruption · latest
Minor disruption due to consultant output and review timeframes and complexity of project. Eight Councillor workshops completed. Internal consultation, review of proposed actions and financial analysis being undertaken on draft. Delivery of the draft Report and recommendations proposed by June 2026.
5.2.2
Q3 · On Track · latest
Rectification works ongoing at Noosa Leisure Centre Cooroy Library and The J. Rectifications works completed at Noosaville Library with new solar scheduled by end 2026. Emissions reduction capital works PID for 26/27 submitted for future works.
2 initiatives
2.4.5
Q4 · On Track · latest
The Go Noosa program was delivered for the 2024/25 FY. An evaluation report is presented to Council in August 2025.
4.7.1
Q4 · Minor Disruption · latest
Roadmap to Net Zero Emissions project is underway with a series of Councillor workshops. Minor delays experienced due to FY25/26 budget uncertainty for Waste and Recovery Centre master planning, staff resource limitations, procurement, and grant applications. Completion is anticipated for end of Q2 FY25/26.
3 initiatives
4.7.1
Q4 · On Track · latest
Working with Zen Inc on community emissions reduction projects including supporting the EV Expo and "electrify everything" program. Supported Noosa Environment Hub to deliver the Youth Climate Summit. Community education and education program will be developed late 2024. Note-Ongoing and part of BAU
4.7.2
Q4 · On Track · latest
Information provided to businesses on emissions reduction funding and support opportunities via newsletters and industry events. Note-Ongoing and part of BAU
4.7.7
Q4 · Major Disruption · latest
On track for preparation late 2024. Note-relisted in the new 24/25 Operational Plan