6 initiatives across 3 years

Underway this year

1

all on track at end of March 2026

Delivery record

0 of 5

past initiatives completed · 3 on track, not yet complete

2025–261 initiative
4.2.2 Destination Management PlanQ3 · On Track · Creative design of final document and DMP Portal completed with soft launched planned in early Q4. Draft Implementation Plan being updated. Two presentations undertaken with Tourism Noosa Board. One meeting undertaken with Tourism Noosa staff. Presented to the board of Noosa Biosphere Reserve Foundation and to Visit Sunshine Coast. Presentations scheduled with Environmental Groups (NICA, Landcare etc), Business Round Table and Community Associations in early Q4. Soft copies of final document will be sent to other key stakeholders including but not limited to - Department of Tourism, Science and Environment, Tourism and Events Queensland, Tourism Australia and Destination Think (Global Think Tank). Responses to all submissions being prepared and will be sent out prior to soft launch. A media campaign will be implemented following soft launch to keep the Destination Management Plan "live" and at the forefront of the community's minds. Draft TOR for Destination Stewardship Council under development.
2024–252 initiatives · 0 finished on time

4.2.2 Tourism Noosa Partnership · ended the year with minor disruption

Council endorsed a revised 12-month agreement at a Special Meeting in May 2025. Partnership Agreement (including Road Map) under review. Awaiting Q4 Report from Tourism Noosa to enable Annual Review.

4.2.1 Destination Management PlanQ4 · On Track · Individual Project Control Group (PCG) and External Reference Group meetings (15 meetings) were undertaken. Feedback from these meetings were included in the draft DMP document and presented to Council for further consideration. Special Meeting scheduled for August 2025 to endorse the draft DMP for the next phase community engagement.
2023–243 initiatives · 0 finished on time

4.2.1 Destination Management Plan · ended the year with minor disruption

Deep Dive Analysis completed. Community Engagement Phase 2 scheduled for August/September 2024. Note-relisted in the new 24/25 Operational Plan

4.2.2 Destination Management PlanQ4 · On Track · Collaboration on DMP Action Plan (including Deep Dive overlay) is ongoing. Note-relisted in the new 24/25 Operational Plan
4.2.3 Tourism Noosa PartnershipQ4 · On Track · Formal discussions with TN commence in July 2024 and remain conditional on completion of DMP. Note-relisted in the new 24/25 Operational Plan