TOPIC
›
Coastal & foreshore management
FY 2022–23
Q1
Q2
Q3
Q4
1.3.2 Develop the Noosaville Infrastructure Foreshore Management Plan.
Q1
Q2
Consultation is complete, project is on track however paused during Council Caretaker period.
Q3
Q4
The community has been engaged on the 80% masterplan document during Q4 of 2023/24, and Council are working through a variety of feedback with the expectation of an additional community engagement round being required before progressing to 100%. Note-relisted in the new 24/25 Operational Plan
1.3.4 Finalise the Eastern Beaches Foreshore Management Plan.
Q1
Plan complete and endorsed by Council.
FY 2023–24
Q1
Q2
Q3
Q4
1.3.2 Initiate the implementation of the Eastern Beaches Foreshore Management Plan 2023 focusing on education and awareness of the social and environmental values of foreshores, and key management issues.
Q1
A slower start than planned due to staff resources being diverted. Education material has been finalised.
Q2
Education material complete, public awareness campaign has started, restoration program is underway, beach infrastructure access manual.
Q3
Education material complete, public awareness campaign has started, restoration program is underway within available budget and resourcing, beach infrastructure access manual is 80% developed, community workshop planned for Peregian area.
Q4
Education material is complete, and the public awareness campaign has started. A restoration program is underway within available budget and resourcing, and the beach infrastructure access manual is nearing completion (80%).
FY 2024–25
Q1
Q2
Q3
Q4
1.3.1 Implement the Noosaville Foreshore Infrastructure Master Plan
Q1
20-year plan working through PID initiations like the Changing Places facility and asset renewals with available funding and supporting grant applications. The Changing Places facility has progressed to design development with selected architects, and community engagement has indicated widespread support for the siting and design of the facility.
Q2
The 20-year plan is progressing through PID initiations, including the Changing Places facility and asset renewals supported by available funding and grant applications. The Changing Places facility has progressed to design completion, with community engagement indicating broad support for both the siting and design of the facility. The project is now in the tender phase.
1.3.2 Implement the Eastern Beaches Foreshore Reserves Management Plan
Q1
Programme progressing as planned. contractors have been working through priority areas. community workshop held to highlight management of invasive species in gardens.
Q2
This is an annual implementation program. Works are progressing as planned to deliver resilient ecosystems, community education, and upgraded infrastructure. A key quarterly milestone was the receipt of more than 500 positive responses to the inaugural Foreshore Reserves update.
4.8.6 Progress design for replacement of Main Beach seawall
Q1
Noosa Main Beach Resilience - Initial modelling design completed. Incorporation of feedback is underway. Preliminary work is underway to identify future funding pathways for construction.
Q2
Noosa Main Beach Resilience — Initial modelling and concept design have been completed, with incorporation of stakeholder feedback now underway. Preliminary investigations have commenced to identify future funding pathways for construction. Approvals and delivery timeframes are also being reviewed to ensure alignment and achievement of community outcomes.