3 initiatives across 3 years

Underway this year

1

all on track at end of March 2026

Delivery record

1 of 2

past initiatives completed · 1 on track, not yet complete

2025–261 initiative
1.3.2 Eastern Beaches ForeshoreQ3 · On Track · This is an annual implementation program. Works are progressing as planned to deliver resilient ecosystems within limited budget, community education, and upgraded infrastructure. Turtle engagement material distributed via mail and workshop. Urban Wildlife Gardens event was hosted in conjunction with NICA, targeting engagement with Eastern Beaches residents. Scoping works with Council's Coastal and Foreshore Officer for beach access upgrades has occurred.
2024–251 initiative · 0 finished on time
1.3.2 Eastern Beaches ForeshoreQ4 · On Track · Education material is complete, and the public awareness campaign has started. A restoration program is underway within available budget and resourcing, and the beach infrastructure access manual is nearing completion (80%).
2023–241 initiative · 1 finished on time
1.3.4 Eastern Beaches ForeshoreQ4 · Completed · Plan complete and endorsed by Council.