Pathway renewal

Deliver the pathway renewal program across Council.

Quarterly updates

Q4 · On Track · April to June 2024 · latest

Minor delays have resulted in not all pathways identified for renewal being completed in 23/24. Limited availability of competent contractors have resulted in lesser experienced contractors requiring substantial guidance, supervision and additional time to complete works. Remaining pathways will be completed in 24/25. Note-relisted in the new 24/25 Operational Plan

Q3 · On Track · January to March 2024

Q2 · On Track · October to December 2023

Phase two of the pathway program (14 locations) has been awarded with works commencing in February, 2024.

Q1 · On Track · July to September 2023

Where this sits

Initiative 2.2.3 is from the 2023–24 operational plan and works towards Liveability Objective 2.2: Parks and paths.

This initiative is from a past year and is no longer being updated.