Kabi Kabi Relationship Agreement

Continue implementation of actions in the KKPAC Relationship Agreement and the Kabi Kabi Commitment Implementation Plan.

Quarterly updates

Q3 · Major Disruption · January to March 2026 · latest

Implementation of the program has been constrained by limited staff resources. Additional temporary resource allocation was approved through Budget Review 2 in the first quarter of 2026.

Q2 · Major Disruption · October to December 2025

Implementation of the program is constrained by limited staff resources. Additional resource allocation will be requested through Budget Review 2 in the first quarter of 2026.

Q1 · Major Disruption · July to September 2025

Implementation of the program is constrained by limited staff resources.

Q4 is not due yet.

Where this sits

Initiative 4.1.2 is from the 2025–26 operational plan and works towards Future Objective 4.1: Reconciliation.

Latest status: January to March 2026 · Major Disruption