Woondum and Wahpunga trail upgrades
2 initiatives across 2 years
Underway this year
1
all on track at end of March 2026
Delivery record
0 of 1
past initiatives completed · 1 on track, not yet complete
2025–261 initiative
2.2.1 Noosa Biosphere TrailsQ3 · On Track · Complete work packages currently in construction. Initiated completion reporting requirements. Consolidating remaining work items into packages to be tender-ready, pending approval of scope expansion and approval from grant provider of and extension of time.
2024–251 initiative · 0 finished on time
2.2.1 Noosa Biosphere TrailsQ4 · On Track · Project Reference Group has been re-established to guide scope of works. On the ground works has commenced, with ongoing procurement and scope refinement underway for remaining works to meet grant obligations. QPWS permit Section 34 application for all trails progressing well. This project is funded until November 2026.