Operational Plan 2024-25
Initiative 3.7.2: Implement best practice waste management practices and continuous improvement across all waste functions and assets to support the principles of the waste hierarchy and actions in the Waste Plan.
Q1:On Track
Continuous improvement weekly via team KPI meetings. Noosa Council has taken over operational responsibility of the Transfer station (Eumundi Road) with a view to improve diversion and recycling rates.
Q2:On Track
Waste Plan 2023-2027 action tracker has been developed with a project plan to support delivery of key milestones. This is monitored by the team monthly.
Q3:On Track
Waste Plan 2023-2027 action tracker has been developed with a project plan to support delivery of key milestones. This is monitored by the team monthly. Recent environmental performance reporting has shown ongoing reduction in carbon emissions and waste diversion consistent with Waste Plan targets.
Q4:On Track
Waste Plan 2023-2027 action tracker has been developed with a project plan to support delivery of key milestones. This is monitored monthly by the team. Recent environmental performance reporting has shown ongoing reduction in carbon emissions and waste diversion consistent with Waste Plan targets. A project plan for FY25/26 key waste plan actions is being developed and will guide the monthly action plan reporting.
Noosa Shire Council
Operational Plan
2024-25
Initiative 3.7.2: Implement best practice waste management practices and continuous improvement across all waste functions and assets to support the principles of the waste hierarchy and actions in the Waste Plan.
Q1: On Track
Q2: On Track
Q3: On Track
Q4: On Track
Continuous improvement weekly via team KPI meetings. Noosa Council has taken over operational responsibility of the Transfer station (Eumundi Road) with a view to improve diversion and recycling rates.
Waste Plan 2023-2027 action tracker has been developed with a project plan to support delivery of key milestones. This is monitored by the team monthly.
Waste Plan 2023-2027 action tracker has been developed with a project plan to support delivery of key milestones. This is monitored by the team monthly. Recent environmental performance reporting has shown ongoing reduction in carbon emissions and waste diversion consistent with Waste Plan targets.
Waste Plan 2023-2027 action tracker has been developed with a project plan to support delivery of key milestones. This is monitored monthly by the team. Recent environmental performance reporting has shown ongoing reduction in carbon emissions and waste diversion consistent with Waste Plan targets. A project plan for FY25/26 key waste plan actions is being developed and will guide the monthly action plan reporting.