Operational Plan
2023-24
›
Initiative 4.4.1: Initiate preparation of an Advocacy Plan that addresses top 10 Shire wide issues and infrastructure needs.
Q1:On Track
Due for initiation in 2024.
Q2:On Track
Preparation commenced, briefing note to be reported to the Executive Team.
Q3:On Track
Q4:Major Disruption
This was not delivered last year due to competing priorities however a list of key advocacy issues was prepared for the Mayor for the Comseq Ministerial delegation. Note-relisted in the new 24/25 Operational Plan
Noosa Shire Council
Operational Plan
2023-24Initiative 4.4.1: Initiate preparation of an Advocacy Plan that addresses top 10 Shire wide issues and infrastructure needs.
Q1: On Track
Q2: On Track
Q3: On Track
Q4: Major Disruption
Due for initiation in 2024.
Preparation commenced, briefing note to be reported to the Executive Team.
This was not delivered last year due to competing priorities however a list of key advocacy issues was prepared for the Mayor for the Comseq Ministerial delegation. Note-relisted in the new 24/25 Operational Plan