Initiative 3.5.1: Complete amendments to Noosa Plan 2020 to support and enable the Innovation precinct at the Shire Business Centre to develop.
Q1:On Track
Proposed planning scheme amendments public notified. Submissions being reviewed and workshopped with Councillors. Regular discussion with Stockwell. Not a current priority for developer. Agreed to share investment leads.
Q2:On Track
Amendments package endorsed by Council in December 2024. Activation discussions continue with Stockwell Group.
Q3:On Track
Final amendments submitted to State February 2025 awaiting Ministerial approval for adoption and commencement. Activation discussions continue with Stockwell Group.
Q4:Minor Disruption
Final amendments submitted to State February 2025, now awaiting Ministerial approval for adoption and commencement. Activation discussions continue with Stockwell Group.
Noosa Shire Council
Operational Plan
2024-25Initiative 3.5.1: Complete amendments to Noosa Plan 2020 to support and enable the Innovation precinct at the Shire Business Centre to develop.
Q1: On Track
Q2: On Track
Q3: On Track
Q4: Minor Disruption
Proposed planning scheme amendments public notified. Submissions being reviewed and workshopped with Councillors. Regular discussion with Stockwell. Not a current priority for developer. Agreed to share investment leads.
Amendments package endorsed by Council in December 2024. Activation discussions continue with Stockwell Group.
Final amendments submitted to State February 2025 awaiting Ministerial approval for adoption and commencement. Activation discussions continue with Stockwell Group.
Final amendments submitted to State February 2025, now awaiting Ministerial approval for adoption and commencement. Activation discussions continue with Stockwell Group.