1.8.1 Continue to update and maintain the Noosa Plan 2020 through various amendments to incorporate and respond to new, revised, or updated Council strategies, policies and requirements.
Q1
Amendments package still with State government awaiting sign off of State Interest for public consultation.
Q2
Amendments package still with State government awaiting sign off of State Interest for public consultation.This will now not be considered until the new Council.
Q3
Awaiting State Government Ministerial sign off, the amendments have been with the State for 12 months and with the Minister for 2 months. Note-previously experienced a minor disruption, now experiencing a major disruption
Q4
Public consultation undertaken for Noosa Plan 2020 Amendment 2. Next step is to respond to submissions and report back to council for endorsement prior to submission for State Government Ministerial sign off. Note-relisted in the new 24/25 Operational Plan
3.5.2 Complete amendments to Noosa Plan to support and enable the Innovation precinct at the Shire Business Centre to develop.
Q1
Amendments with State Government awaiting sign off of first state interest for public consultation.
Q2
Amendments with State Government awaiting sign off of first state interest for public consultation. This will now not occur before the caretaker period and will be considered by the new Council.
Q3
Awaiting State Government Ministerial sign off, the amendments have been with the State for 12 months and with the Minister for 2 months. Note-as previously reported
Q4
Proposed amendments currently on public notification until 14 July 2024. Note-relisted in the new 24/25 Operational Plan
FY 2023–24
Q1
Q2
Q3
Q4
3.5.1 Complete amendments to Noosa Plan 2020 to support and enable the Innovation precinct at the Shire Business Centre to develop.
Q1
Proposed planning scheme amendments public notified. Submissions being reviewed and workshopped with Councillors. Regular discussion with Stockwell. Not a current priority for developer. Agreed to share investment leads.
Q2
Amendments package endorsed by Council in December 2024. Activation discussions continue with Stockwell Group.
Q3
Final amendments submitted to State February 2025 awaiting Ministerial approval for adoption and commencement. Activation discussions continue with Stockwell Group.
Q4
Final amendments submitted to State February 2025, now awaiting Ministerial approval for adoption and commencement. Activation discussions continue with Stockwell Group.
4.4.1 Finalise the amendments to the Noosa Plan 2020 and seek to implement the Noosa Housing Strategy 2022 to address housing challenges faced by our residents.
Q1
At Council's request the consultation period on the proposed planning scheme amendments was extended. Reviewing submissions and workshopping issues with Councillors. Adopt-a-Worker funding included in Noosa Council's State Election Advocacy Document.
Q2
Proposed amendments publicly notified and report to Council in December 2024. Consultation report prepared and submitters being notified January 2025. Revised amendments being prepared for 2nd state interest check.
Q3
Final amendments submitted to state in February 2025 awaiting Ministerial approval for adoption and commencement.
Q4