TOPIC
›
Shoreline Erosion Management Plan
FY 2022–23
Q1
Q2
Q3
Q4
1.3.3 Implement the Noosa Heads Main Beach Shoreline Erosion Management Plan (SEMP).
Q1
Absence of visible progress resulted in the halt of the 2023 nourishment works. Works are being retendered for completion by a new dredging contractor. Commencement would be April 2024, unless State authorities approve Council's request for an earlier commencement.
Q2
Dredging and renourishment works for the SEMP project have been awarded with target commencement in April 2024 (pending State authorities approve Councils request for an earlier commencement). An asset renewal program will be required to maintain the shoreline following works completion. Revised anticipated completion date 30/9/24.
Q3
Dredging and renourishment works for the SEMP project have commenced and anticipated for completion by end September 2024. An asset renewal program will be required to maintain the shoreline following works completion. Note-as previously reported
Q4
Dredging and renourishment works for the SEMP project were completed June 2024. Some additional channel formation is also completed, and an asset renewal program will be required to maintain the shoreline following works completion.
FY 2023–24
Q1
Q2
Q3
Q4
1.3.5 Implement the Noosa Spit Shoreline Erosion Management Plan (SEMP) to protect the Noosa Spit and river estuary (incl. sand and Noosaville foreshores) from major coastal events.
Q1
This project was completed in August 2024.
FY 2024–25
Q1
Q2
Q3
Q4
4.8.6 Progress design for replacement of Main Beach seawall
Q1
Noosa Main Beach Resilience - Initial modelling design completed. Incorporation of feedback is underway. Preliminary work is underway to identify future funding pathways for construction.
Q2
Noosa Main Beach Resilience — Initial modelling and concept design have been completed, with incorporation of stakeholder feedback now underway. Preliminary investigations have commenced to identify future funding pathways for construction. Approvals and delivery timeframes are also being reviewed to ensure alignment and achievement of community outcomes.