Noosa District Sports Complex
3 initiatives across 3 years
Underway this year
1
all on track at end of March 2026
Delivery record
0 of 2
past initiatives completed · 1 on track, not yet complete
2025–261 initiative
2024–251 initiative · 0 finished on time
2.5.2 Sports complex master plans · ended the year with minor disruption
Noosa District Netball Clubhouse rebuild underway with an anticipated completion in August 2025. Internal road upgrade at NDSC subject to design and external funding opportunities. Cooroy Sports Complex: • Field lighting upgrades to be completed and handed over by August 2025. • Gymnastics and multi-use area upgrades detailed design has been completed, now awaiting final costings and approval to go to tender for construction. • Internal road and car park upgrades on hold until capital works allocation allocated.