Cooroy Sports Complex

3 initiatives across 3 years

Underway this year

1

all on track at end of March 2026

Delivery record

0 of 2

past initiatives completed · 1 on track, not yet complete

2025–261 initiative
2.5.2 Sports complex master plansQ3 · On Track · The Cooroy Oval lighting project is complete. The Cooroy Gymnastics extension project continues to progress, as does the completion of the Noosa Netball Clubhouse at NDSC, both being delivered as projects arising from the precinct master planning process.
2024–251 initiative · 0 finished on time

2.5.2 Sports complex master plans · ended the year with minor disruption

Noosa District Netball Clubhouse rebuild underway with an anticipated completion in August 2025. Internal road upgrade at NDSC subject to design and external funding opportunities. Cooroy Sports Complex: • Field lighting upgrades to be completed and handed over by August 2025. • Gymnastics and multi-use area upgrades detailed design has been completed, now awaiting final costings and approval to go to tender for construction. • Internal road and car park upgrades on hold until capital works allocation allocated.

2023–241 initiative · 0 finished on time
2.5.2 Sports complex master plansQ4 · On Track · Implementation across both sites is ongoing with projects listed in 10 year CW pipeline. Cooroy Gymnastics clubhouse expansion is in funding stages, as is field lighting in 24/25 CWP. Note-relisted in the new 24/25 Operational Plan