Movement and Connection
2 initiatives across 2 years
Underway this year
1
all on track at end of March 2026
Delivery record
0 of 1
past initiatives completed · 1 on track, not yet complete
2025–261 initiative
2.4.2 Movement and Connection Delivery PlanQ3 · On Track · The Movement and Connection Delivery Plan report has been finalised and reviewed. The report is scheduled for presentation to the June Ordinary Meeting for Council endorsement.
2024–251 initiative · 0 finished on time
2.4.1 Movement and Connection Delivery PlanQ4 · On Track · Review of actions included in the Transport Plan and Cycling and Walking Strategy has been undertaken. A draft Delivery Plan has been prepared for internal review. The draft was discussed at Councillor workshop in April 2025.