Operational Plan
2024-25
›
Initiative 4.5.1: Complete the Place Pilot Program in Pomona and share learnings to improve the future of the program and inform future planning for Pomona.
Q1:Minor Disruption
Stage 3 community consultation on the Draft Pomona Place Plan has been delayed until October 24 to allow for community consultation on other projects to proceed.
Q2:On Track
The Place Pilot Program Plan has been finalised and will be reported to Council for endorsement in March 2025.
Q3:On Track
Final Pomona Place Plan endorsed by Council March 2025. Evaluation report under preparation.
Q4:On Track
Final Pomona Place Plan endorsed by Council March 2025. Evaluation report to be submitted to Council in August 2025.
Noosa Shire Council
Operational Plan
2024-25Initiative 4.5.1: Complete the Place Pilot Program in Pomona and share learnings to improve the future of the program and inform future planning for Pomona.
Q1: Minor Disruption
Q2: On Track
Q3: On Track
Q4: On Track
Stage 3 community consultation on the Draft Pomona Place Plan has been delayed until October 24 to allow for community consultation on other projects to proceed.
The Place Pilot Program Plan has been finalised and will be reported to Council for endorsement in March 2025.
Final Pomona Place Plan endorsed by Council March 2025. Evaluation report under preparation.
Final Pomona Place Plan endorsed by Council March 2025. Evaluation report to be submitted to Council in August 2025.