TOPIC
›
Eastern Beaches Foreshore Management Plan
FY 2022–23
Q1
Q2
Q3
Q4
1.3.4 Finalise the Eastern Beaches Foreshore Management Plan.
Q1
Plan complete and endorsed by Council.
FY 2023–24
Q1
Q2
Q3
Q4
1.3.2 Initiate the implementation of the Eastern Beaches Foreshore Management Plan 2023 focusing on education and awareness of the social and environmental values of foreshores, and key management issues.
Q1
A slower start than planned due to staff resources being diverted. Education material has been finalised.
Q2
Education material complete, public awareness campaign has started, restoration program is underway, beach infrastructure access manual.
Q3
Education material complete, public awareness campaign has started, restoration program is underway within available budget and resourcing, beach infrastructure access manual is 80% developed, community workshop planned for Peregian area.
Q4
Education material is complete, and the public awareness campaign has started. A restoration program is underway within available budget and resourcing, and the beach infrastructure access manual is nearing completion (80%).
FY 2024–25
Q1
Q2
Q3
Q4
1.3.2 Implement the Eastern Beaches Foreshore Reserves Management Plan
Q1
Programme progressing as planned. contractors have been working through priority areas. community workshop held to highlight management of invasive species in gardens.
Q2
This is an annual implementation program. Works are progressing as planned to deliver resilient ecosystems, community education, and upgraded infrastructure. A key quarterly milestone was the receipt of more than 500 positive responses to the inaugural Foreshore Reserves update.