TOPIC
›
Bushland Care Guideline
FY 2023–24
Q1
Q2
Q3
Q4
1.2.2 Continue to deliver a Community Bushcare Program for active volunteers across bushland care groups and undertake a review of the Community Bushland Care Guideline.
Q1
All Community Bushcare Volunteer groups have received officer support. Appointment of weekend contractor complete.
Q2
Annual programs on-track for 2025 for all bush-care groups.
Q3
Annual programs on-track for 2025 for all bush-care groups
Q4
Annual programme for all Volunteer Bushcare groups successfully delivered.
FY 2024–25
Q1
Q2
Q3
Q4
1.2.2 Deliver the Community Bushcare Program and review the Bushland Care Guideline
Q1
The program is progressing as planned. While one of the two key staff members is currently unavailable, coverage is being effectively managed through support from other team members within the branch.
Q2
The program is progressing as planned. While one of the two key staff members is currently unavailable, coverage is being effectively managed through support from other team members within the branch. New programming for 2026 is being developed prior to the working bee season commencing in Feb 2026.