Bushfire management & fuel reduction
FY 2022–23
Q1
Q2
Q3
Q4
1.2.1 Continue to deliver the Noosa Bushland Reserve Strategic Fire Management Plan 2021 and deliver planned burns and mechanical fuel reduction where conditions allow.
Q1
Q2
Fire program delivered within operational capacity. Some limitations due to prevailing conditions not allowing full planned burn program to be undertaken.
Q3
Q4
Program successfully delivered.
FY 2023–24
Q1
Q2
Q3
Q4
1.2.1 Continue to deliver the Noosa Bushland Reserve Strategic Fire Management Plan 2021 and deliver planned burns and mechanical fuel reduction where conditions allow in priority reserves, based on a comprehensive bushfire risk assessment.
Q1
Program planning being undertaken for 2025 program. Some late burns undertaken due to favourable weather conditions.
Q2
Program planning being undertaken for 2025 program. Some late burns undertaken due to favourable weather conditions. Fire trail maintenance program focus for the next 4 weeks.
Q3
Program planning completed for 2025 burns. Maintenance of trails and breaks are being undertaken. Planned Burns are now underway as weather permits.
Q4
Program planning completed for 2025 burns. Planned burns being undertaken as weather and conditions allow throughout Q4. As we are at the mid-point of the programme, we will not have a clear picture of completion until Q1 reporting of FY25/26.
FY 2024–25
Q1
Q2
Q3
Q4
1.2.1 Deliver the Bushland Reserve Strategic Fire Management Plan including planned burns and fuel reduction
Q1
Minor disruption due to current vacancy of Senior Fire Management Officer - currently undergoing recruitment. This has delayed some of the planning at this stage of the year. Contingency measures involve redirecting internal branch resources for support at this time. It is anticipated that the current recruitment will not affect the final delivery of the programme.
Q2
Due to the high volume of strategic plans currently being reviewed and developed within the Environmental Services Branch, the delivery timeframe for this initiative has been amended to the end of the calendar year, to ensure sufficient management and staff capacity can be allocated.