3 initiatives across 3 years
Underway this year
1
all on track at end of March 2026
Delivery record
0 of 2
past initiatives completed · 2 on track, not yet complete
2025–261 initiative
2.7.3 Noosa Leisure and Aquatic CentresQ3 · On Track · Upgrades across both facilities are subject to ongoing review, with filtration system upgrades at the Noosa Aquatic Centre currently in the procurement stage, and the security fencing project at the Noosa Leisure Centre completed. The NLC project is on hold until a Business Case process has funding to complete this piece of work
2024–251 initiative · 0 finished on time
2.7.2 Noosa Leisure and Aquatic CentresQ4 · On Track · NLC Needs Assessment completed with further work required to progress project into next stages and NAC project at latter stages of delivery.
2023–241 initiative · 0 finished on time
2.7.2 Noosa Leisure and Aquatic CentresQ4 · On Track · NLC Needs assessment project is nearing completion, and NAC Needs Assessment and Master Plan process is well underway with consultant. Note-relisted in the new 24/25 Operational Plan