Landfill
4 initiatives across 3 years
Underway this year
1
all on track at end of March 2026
Delivery record
1 of 3
past initiatives completed · 2 on track, not yet complete
2025–26
3.7.1 Waste diversionQ3 · On Track · Compost tender in final stages of negotiation of contract for commercial departures. Design work expected to be completed end of calendar year 2026. Capping underway again following ordinary meeting approval for use of engineered capping solution. To be procured in 2026 for installation Q3/Q4 FY26/27. DA with SARA for Solar. DA for master plan approved, funding unlikely and waste projects team is rescoping and restaging the masterplan works for future capital years. Electrical enabling works and design underway for main switch board and generator backup for resilience and recovery.
2024–25
1 initiative · 0 finished on time
3.7.1 Resource Recovery FacilityQ4 · On Track · Key projects within stage 1 of the Masterplan have advanced with a Development Application lodged in February 2025 for Council consideration to provide for a shovel ready project. Grant funding application has been submitted with the Federal Government. High level concept designs completed. Waiting on funding update.
2023–24
2 initiatives · 1 finished on time
3.7.5 Resource Recovery FacilityQ4 · On Track · Stage 1 of the Noosa Landfill and Resource Recovery Facility Master Plan is complete and going to Council for endorsement in the first quarter of the new financial year. Note-relisted in the new 24/25 Operational Plan
3.7.6 Waste diversionQ4 · Completed · Reverse Vending Machine (RVM) trial is now complete, as well as the purchase of RVM for the Eumundi Road Landfill.