4 initiatives across 3 years

Underway this year

1

all on track after Q3

Delivery record

1 of 3

past initiatives completed

3.7.1

Deliver the Noosaville Resource Recovery Area Waste Master Plan as funding becomes available including environmental and safety compliance, new capping program, new waste diversion facilities and innovative waste practices, such as composting.

Q3 · On Track · latest

Compost tender in final stages of negotiation of contract for commercial departures. Design work expected to be completed end of calendar year 2026. Capping underway again following ordinary meeting approval for use of engineered capping solution. To be procured in 2026 for installation Q3/Q4 FY26/27. DA with SARA for Solar. DA for master plan approved, funding unlikely and waste projects team is rescoping and restaging the masterplan works for future capital years. Electrical enabling works and design underway for main switch board and generator backup for resilience and recovery.

1 initiative
3.7.1

Develop the Noosa Landfill and Resource Recovery Facility Master Plan to provide future direction in the management of the Resource recovery centre and maximise waste diversion and minimisation practices.

Q4 · On Track · latest

Key projects within stage 1 of the Masterplan have advanced with a Development Application lodged in February 2025 for Council consideration to provide for a shovel ready project. Grant funding application has been submitted with the Federal Government. High level concept designs completed. Waiting on funding update.