Deliver the Noosaville Resource Recovery Area Waste Master Plan as funding becomes available including environmental and safety compliance, new capping program, new waste diversion facilities and innovative waste practices, such as composting.
Q3 · On Track
Compost tender in final stages of negotiation of contract for commercial departures. Design work expected to be completed end of calendar year 2026. Capping underway again following ordinary meeting approval for use of engineered capping solution. To be procured in 2026 for installation Q3/Q4 FY26/27. DA with SARA for Solar. DA for master plan approved, funding unlikely and waste projects team is rescoping and restaging the masterplan works for future capital years. Electrical enabling works and design underway for main switch board and generator backup for resilience and recovery.