TOPIC
›
flood resilience
FY 2024–25
Q1
Q2
Q3
Q4
4.8.8 Advance flood resilience projects including flood studies
Q1
Minor disruptions due to staff resourcing and capacity. Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 commencing November 2025. Noosa Flood Management Operational Plan prepared for implementation with internal working group.
Q2
Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 commenced November 2025 and due by June 2026. Implementation of the Noosa Flood Management Operational Plan commenced with internal working group.