LOCATION TAG
Six Mile Creek
2025-26
Q1
Minor Disruption
Minor disruptions due to staff resourcing and capacity. Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 commencing November 2025. Noosa Flood Management Operational Plan prepared for implementation with internal working group.
Q2
On Track
Noosa River Flood Study and Six Mile Creek study on track for delivery June 2026. Lake Entrance Boulevard Flood Study Phase 2 commenced November 2025 and due by June 2026. Implementation of the Noosa Flood Management Operational Plan commenced with internal working group.
2024-25
Q1
On Track
Flood Management Operational Plan complete, currently creating a summarised version for broader distribution. Noosa River Flood Study and Six Mile Creek Flood Study updates are on track with data collation and model establishment phase of project underway. Estimated completion June 2025.
2023-24
Q4
Minor Disruption
Flood Management Operational Plan in final draft. Noosa River Flood Study and Six Mile Creek Flood Study updates are on track with ITQ now closed and tender evaluation and award to be completed within Q1. Estimated completion June 2025. Note-relisted in the new 24/25 Operational Plan