The current funding amount estimated to be recoverable from QRA for flood reconstruction works is $147.6m. Works are progressing as per most recent plans discussed with QRA. Council is reporting progress of site completion at 48%. The completed sites construction has been focused on road resurfacing, smaller landslides and stormwater structures. There are 16 sites currently in delivery phase, including Black Mountain. This site continues to progress as expected with key construction activities continuing mostly on plan. The remaining two precincts (Schreibers Rd Bridge and Upper Pinbarren Creek Rd Landslides) are currently finalising design in preparation or tender actions to commence in February.