LOCATION TAG
Black Mountain
2024-25
Q1
On Track
All landslide reconstruction completed except for Black Mountain Rd, Black Pinch Rd and Upper Pinbarren Creek Rd. Those projects are on track. All waterway crossing reconstruction completed except for Schreibers Rd Bridge Betterment project. This project has recently commenced constructon with possession of site.
Q4
On Track
Majority of reconstruction projects complete including major Black Mountain landslip. Final reconstruction project near completion. Human social Recovery Plan completed.
2023-24
Q2
On Track
The current funding amount estimated to be recoverable from QRA for flood reconstruction works is $147.6m. Works are progressing as per most recent plans discussed with QRA. Council is reporting progress of site completion at 48%. The completed sites construction has been focused on road resurfacing, smaller landslides and stormwater structures. There are 16 sites currently in delivery phase, including Black Mountain. This site continues to progress as expected with key construction activities continuing mostly on plan. The remaining two precincts (Schreibers Rd Bridge and Upper Pinbarren Creek Rd Landslides) are currently finalising design in preparation or tender actions to commence in February.